3.5: HWE.3 Hardware Implementation
Process Purpose: Execute the detailed design (HWE.2) - source components, fabricate PCBs, assemble boards, perform basic functionality checks. Deliver physical hardware ready for verification testing.
Implementation Activities
1. Component Procurement
Process:
- Issue purchase orders (POs) to qualified suppliers
- Verify component authenticity (counterfeit detection)
- Store components in controlled conditions
- Track traceability (batch codes, lot numbers)
Component Sourcing Challenges:
Microcontroller (STM32H755ZI):
├─ Lead time: 16 weeks (typical for safety-critical)
├─ Minimum order: 500 units
├─ Supplier: STMicroelectronics official distributor
└─ Verification: Datasheet, certificate of conformance
Sensor (RTD Pt100):
├─ Lead time: 8 weeks
├─ Source: Multiple suppliers (reduce risk)
└─ Verification: Calibration certificate, accuracy tolerance
Counterfeit Risk Mitigation:
├─ Purchase from authorized distributors only
├─ Request certificates of conformance
├─ Conduct incoming inspection (visual, continuity test)
└─ Implement traceability (lot tracking in assembly)
2. PCB Fabrication
Vendor Selection:
- IPC Class 2 (general electronics) or Class 3 (safety-critical)
- Controlled impedance (for signal integrity)
- Trace width/spacing compliance
- Flying probe testing (open/short circuits)
Fabrication Spec:
Layer count: 4 layers
Material: FR-4, Tg ≥170°C
Copper weight: 1 oz (top/bottom), 2 oz (inner power/ground)
Via size: 0.010" drill, 0.019" pad
Trace width: ≥4 mil (signal), ≥8 mil (power)
Solder mask: LPI (liquid photoimageable)
Silkscreen: Component labels, orientation marks
Quality Assurance:
- [PASS] Automated Optical Inspection (AOI)
- [PASS] Flying probe test (connectivity)
- [PASS] X-ray inspection (via quality)
- [PASS] Certificate of conformance provided
3. Component Assembly
Method: Pick-and-place with reflow soldering (surface-mount)
Process Steps:
Step 1: PCB Preparation
├─ Solder paste application (stencil printing)
└─ Inspection: Paste coverage ≥90%
Step 2: Component Placement
├─ Automated pick-and-place machine
├─ Vision-guided placement (±0.1mm accuracy)
└─ Inspection: Component orientation, placement accuracy
Step 3: Reflow Soldering
├─ Thermal profile (ramp-up, peak, cool-down)
├─ Peak temperature: 245-260°C
├─ Time above liquidus (217°C): 60-90 seconds
└─ Cool-down rate: <6°C/second (avoid thermal stress)
Step 4: Quality Inspection
├─ Automated Optical Inspection (AOI)
├─ X-ray inspection (solder joint quality)
└─ Manual rework (any defects)
Step 5: Functional Test (Basic)
├─ Power supply (voltage, current)
├─ Oscillator (frequency accuracy)
├─ GPIO (input/output response)
└─ Pass/fail rate target: >99%
4. Traceability & Documentation
Traceability Implementation:
Component Traceability Chain:
├─ Supplier (STMicroelectronics official distributor)
├─ PO number (PO-2025-1234)
├─ PCB lot (PCB-Lot-2025-056)
├─ Assembly date (2025-12-15)
├─ Assembly batch (Batch-A-2025-12)
├─ Serial number (HW-001-2025)
└─ Test date (2025-12-20)
Documentation:
├─ Bill of Materials (BOM) with part numbers
├─ Assembly work instructions
├─ Solder profiling (temperature log)
├─ Test results (pass/fail per board)
└─ Assembly photos (quality evidence)
Manufacturing Defect Management
Defect Categories
| Defect | Root Cause | Detection | Fix |
|---|---|---|---|
| Cold Solder Joint | Low reflow temp | X-ray, electrical test | Rework |
| Tombstoning | Uneven solder paste | AOI | Rework |
| Missing Component | Pick-and-place failure | AOI, functional test | Rework |
| Wrong Component | PO/assembly error | Schematic check | Scrap/Rework |
| Counterfeit Component | Supplier fraud | Incoming inspection | Reject lot |
Yield Analysis
Target: 98% first-pass yield
Actual Results (100 boards):
├─ Pass: 97 boards (97% yield)
├─ Failures: 3 boards
│ ├─ Cold solder joints (2 boards) → Rework
│ └─ Missing capacitor (1 board) → Scrap
└─ After rework: 99 boards (99% yield)
Actions:
├─ Reflow oven calibration (improve temperature uniformity)
├─ Pick-and-place verification (detect missing component)
└─ Target next batch: ≥99%
Documentation Deliverables
HWE.3 Outputs:
- Manufacturing Records (POs, receipts, traceability)
- Assembly Work Instructions (step-by-step procedures)
- Test Records (pass/fail results per board, defect logs)
- Configuration Baseline (BOM revision, solder profile settings)
- Traceability Matrix (component lot → board serial number)
Summary
HWE.3 Outcomes:
- [PASS] PCBs fabricated per design specification
- [PASS] Components sourced and verified (counterfeit-free)
- [PASS] Boards assembled with >99% yield
- [PASS] Functional tests passed (basic power-up test)
- [PASS] Traceability established (lot tracking)
- [PASS] Ready for detailed verification testing (HWE.4)
Next: HWE.4 (Verification testing)